Subgrade Preparation 

  1. Excavate and shape foundation soils.

  2. Ensure foundation soil meets minimum strength requirements through proof rolling or other conventional method. If unacceptable foundation soils are encountered, excavate and replace with suitable quality material. Separation Layer and Base Materials Installation

  3. When separation between subgrade soil and infill material is required, place geotextile over subgrade.

  4. If additional base materials or engineered soils are required between separation geotextile and Retaining wall geocell, install the appropriate depth and compact to a minimum 95 percent Standard Proctor or 90-92 percent Modified Proctor test - dependent upon locale and soil conditions. COREgeocell Panel Placement and Connection

  5. Position and expand gravel grid geocell panels to the appropriate dimensions. Hold individual panels in their expanded positions with rebar J-pins or wooden stakes. Join panels using traditional stapling methods or connecting studs.

  6. Confirm each geo cell panel is expanded uniformly and correctly aligned. Nest panels along each joint to ensure adjacent hdpe geocell panels are flush at joint and adjoining cells are fully anchored. Alternate the installation of rebar J-pins or wooden stakes to ensure each panel is stable Exposed Aggregate or Engineered Infill

  7. Fill honeycomb geocell with specified aggregate material progressively from front to back. Be sure to use an infill material with particle sizes appropriate for the specified depth of the plastic geocell.

  8. For vegetative walls fill inner cells progressively with aggregate infill material. Limit the drop height of infill material to 1m to avoid displacement of the cell wall. Fill outer cells with soil to allow vegetation to grow.

  9. Overfill cells to allow for layered compaction, as the structure forms. Ensure to stagger rebar J-Pins on each layer.

  10. Compact infill to a minimum of 95 percent Standard Proctor or 90-92 percent Modified Proctor test. Surface Drain Compacted Granular Soil Gravel Subsoil drainage pipe wrapped in geotextile Outer geocell cells filled with topsoil and vegetated GD geocell can be used to retain infill in gravity retaining and free standing walls, embankments and barriers. The shear strength of the infill is enhanced by confining material within each cell. When installed in layers, geocell forms an integrated structural mass resisting lateral pressure and movement. Gravel geocell is easily dismantled and may be subsequently re-used.

    Geocell can be used to retain infill in gravity retaining and free standing walls, embankments and barriers. The shear strength of the infill is enhanced by confining material within each cell. When installed in layers, GD geocell forms an integrated structural mass resisting lateral pressure and movement. GD geocell is easily dismantled and may be subsequently re-used. If you have any needs or questions, please feel free to contact us, Mary +8618130028453, mary@zhongloo.com, Anhui Zhonglu (www.zlgeo.com).

  +86-18095658976
 +86-551-65540070
   shaun@zhongloo.com
  Innovation Entrepreneurship Park Economic Development District in Hefei, Anhui China
Copyright © 2021 Anhui Zhonglu Engineering Materials Co., Ltd. | Sitemap    Support by Leadong